0.25 acre x 10 days = 2.5 acres (which is just over 1 hectare). That’s very easily achievable, and should only require a single pass as a half decent operator should have time to keep the job and tip tidy and trim up etc whilst waiting for the dumper to return.
Worst case if they decide to have the tip further away just price in a second/third etc dumper. The only additional consideration then would be keeping the tip tidy if it is a long way from the dig.
My mistake. in my head i'm thinking 5ha total whereas obviously i asked for a time to do 1 hectare. sorry!
 
V8Druid

V8Druid

do it as well as you can,but learn to do it better
My mistake. in my head i'm thinking 5ha total whereas obviously i asked for a time to do 1 hectare. sorry!
a not so senior moment then ..... 's not just me this morning :LOL:
 
Storrsy

Storrsy

Well-known member
Would a couple of 6 ton dumpers not be quicker if ground allows. Would think if 200m haul that would be about the right turn around on a 6 ton dumper. 9 tonners there could be some waiting around.
 
D

DaveDCB

Well-known member
Still confused So are you clearing 5ha or 1? two different jobs…
My mistake. in my head i'm thinking 5ha total whereas obviously i asked for a time to do 1 hectare. sorry!
 
D

DaveDCB

Well-known member
5 ha's is over 12 acres..... thats a fair lump of ground. Id definitely be thinking dozer
Surely not if you have to push it one end to another? Fair enough if it was a huge long strip oppose to a square block? Some push otherwise.. 5ha is 20+ton and a couple of adts with a dozer tidying up the dig and probably one on the tip?
 
V8Druid

V8Druid

do it as well as you can,but learn to do it better
Surely not if you have to push it one end to another? Fair enough if it was a huge long strip oppose to a square block? Some push otherwise.. 5ha is 20+ton and a couple of adts with a dozer tidying up the dig and probably one on the tip?
you missing some zeroes Dave ?? .. or do you mean a 20+ tonner
 
V8Druid

V8Druid

do it as well as you can,but learn to do it better
5ha approx but in small half hectare sections
so roughly acre patches to deal with ... DX140LCR with blade and a couple of dumpers :rolleyes: ... how far apart are the patches doob?
 
Giles

Giles

Well-known member
Just go in at day rate for 3 ton and track dumper be nice little job few weeks haha you boys getting all excited with 20 tonners and adts the soil compaction would be horrendous it isn’t hs2 small section like your saying we’d go in with 5 ton on 550mm pads 5 ton dumper do 1 a day nice little job.

And @doobin i want insinuating you don’t know how to roll bracken I was replying to Cheshire lad about flail and spray.
 
doobin

doobin

Well-known member
Just go in at day rate for 3 ton and track dumper be nice little job few weeks haha you boys getting all excited with 20 tonners and adts the soil compaction would be horrendous it isn’t hs2 small section like your saying we’d go in with 5 ton on 550mm pads 5 ton dumper do 1 a day nice little job.

And @doobin i want insinuating you don’t know how to roll bracken I was replying to Cheshire lad about flail and spray.
You mean an acre a day?
 
JD450A

JD450A

Moderattor🐾
I stand by my original opinion and comment........ Fyi that was based on a hectare.

For reference 100mm is less than you would tend to strip off topsoil. And it's light fluffy material. Scrape, load in a tracked dumper, and repeat..... In the tip cycle you will have time to gather another load up.... rotary tracked dumpers aswell please.
 
Giles

Giles

Well-known member
You mean an acre a day?
You said half hectare section which is an acre ish basically small paddock 2 guys strip and move that with a 5 ton machine and 5 ton track dumper in a full day assuming its not thick but Rory’s right if you've got access to bigger kit and access ok between sites then bigger machine better upto a point
 