Well-known member
36 ton with a tilty on a job like that would piss over a 20 ton long reach.He'd be more productive if he had the tracks the right way for the job, or a better suited machine to the task following on the trim (20t long reach)
A tilty will reduce load capacity on a machine that size drastically. And in price per cube cost it'll be more detrimental than multiple pass completion.