New member
Looking to pick peoples brains. We are currently on a large conversion job (part q ). Industrial unit into domestic. It’s transpired that the existing water main is not going to be able to cope with demand. So we are left looking to get a new 63mm supply in. I have no experience of trenchers would this be an easier option than with the digger. It’s mainly through 2 ag fields approximately 2000m run to the road. We have just put in a new electric supply at 1m depth and it was hard digging. Just wanted a rough idea of price, jobs near Rugby if anyone is interested. Thanks.