New baseline cost estimate for HS2 may not be established until 2026 as project undergoes wholesale reset
Construction on high-speed rail scheme started too early, new chief tells MPswww.building.co.uk
WTF?
" HS2 has begun a full programme reset which may not be complete for more than a year, MPs were told this week.
Senior leaders on the project from the Department for Transport (DfT) and the delivery body itself were subjected to a grilling by the public accounts committee yesterday over the scheme’s rising costs "
and yet more on the debacle ......more HS2 bull sh!t ... " In October transport secretary Louise Haigh said: “ It has long been clear that the costs of HS2 have been allowed to spiral out of control, but since becoming transport secretary I have seen up close the scale of failure in project delivery – and it’s dire.” "
https://www.theconstructionindex.co.uk/news/view/hs2-chief-commits-to-fix-hs2-crisis
![]()
Mark Wild lays bare scale of HS2 failures as he outlines plans to ensure suppliers take on more risk
HS2 chief executive reveals he considered pausing construction to implement 'comprehensive reset' of project
Construction industry ‘not in a fit state’ to deliver HS2, says official review author
James Stewart tells Building government needs to 'proactively' build capacity in the sector to avoid repeat of HS2 failures
HS2 “shambolic mess” says transport secretary
HS2 opening has to be further delayed beyond 2033, the transport secretary told the House of Commons today.
Where HS2 went wrong
The government has published the Stewart Review into what went wrong on HS2.
HS2 to be delayed by at least two years with transport secretary set to highlight ‘litany of failure’ on project
Heidi Alexander due publish findings of two reviews on project today