JD450A
Feral as Fk 🐾
Right, 10' Square 4m deep in waterlogged ground below 1m, Fissure d Clay/Shale type material. Access facilitates a maximum machine size of 7.5t and the biggest lorry I can get in the access is my 15 ton SWB wagon.
Needs to be dug and left open for around 2 days to facilitate installation of a sewage plant.
I'm thinking sheet piles driven in with a EMV and braced.
Any other thoughts and Ideas. Initially I had hoped we would find more solid rock at 2.5m but it's shite at 2.3m (current trench depth) so using the steel sheet and prop shoring I use for trenching won't work. A box is too heavy to crane around with the 7t machine,likewise will be difficult to remove post excavation.
Needs to be dug and left open for around 2 days to facilitate installation of a sewage plant.
I'm thinking sheet piles driven in with a EMV and braced.
Any other thoughts and Ideas. Initially I had hoped we would find more solid rock at 2.5m but it's shite at 2.3m (current trench depth) so using the steel sheet and prop shoring I use for trenching won't work. A box is too heavy to crane around with the 7t machine,likewise will be difficult to remove post excavation.