There was a 3m high H block wall perpendicular to the rear gardens of the houses below, no access to below.
engineer spec was remove and redo with cast in situ.
compromised spec was full excavate 1.4m behind wall, mass fill new footing tide in to old and L bars at front face, drill 50mm weep holes every 1m, install pipe through, then tide existing block wall in with load of screw in V ties the built new block laid flat back face to it and filled with concrete in 450mm lifts. Then clean gravel behind and muck away fill. Awkward Job with no room for anything.
At least you can sleep at night after following the engineering spec. To much risk to contractor doing jobs like this designing it from your own experience .
Fair enough with a free standing wall but not when they are retaining