Cracking!

6

6feetdown

Well-known member
Underpinning single storey extension, limited access 1.9m deep before we hit firm ground, shuttering part complete.
A lot more to do!
20210927_103854.jpg
 

Attachments

  • 20210929_174037.jpg
    20210929_174037.jpg
    260.9 KB · Views: 342
  • 20210929_174103.jpg
    20210929_174103.jpg
    170.4 KB · Views: 350
T whiting

T whiting

Well-known member
It's always scary underpinning the corner it always feels like there's nothing under the house literally!
 
Giles

Giles

Well-known member
My insurance removed under pinning from my most recent renewal, never done much of it and never had a problem but my broker mentioned it recently something about huge problems in London with basements etc I’m only 200 miles from the big smoke lol
 
Last edited:
L

Lynchy

Well-known member

Attachments

  • IMG_20210825_115530_894.jpg
    IMG_20210825_115530_894.jpg
    241.5 KB · Views: 284
  • IMG_20210901_072959_419.jpg
    IMG_20210901_072959_419.jpg
    297.9 KB · Views: 276
  • IMG_20210929_183033_569.jpg
    IMG_20210929_183033_569.jpg
    223.3 KB · Views: 318
Last edited:
B

Brendan

Well-known member
My insurance removed under pinning from my most recent renewal, never done much of it and never had a problem but my broker mentioned it recently something about huge problems in London with basements etc I’m only 200 miles from the big smoke lol
Cant even add it to my policy, the previous renewal which was taken out via a broker with an insurer that if needed could add it, decided when it came to being asked for it that it couldn't be added 🤡

Doesn't underpinning require something like a 30 year guarantee
 
F

fred

Well-known member
Cant even add it to my policy, the previous renewal which was taken out via a broker with an insurer that if needed could add it, decided when it came to being asked for it that it couldn't be added 🤡

Doesn't underpinning require something like a 30 year guarantee

it would be the SE's Prof indem that would be paying out.
 
Bob

Bob

Well-known member
last year during first lockdown I got a bit bored and decided to lift my garage up about 6" at the back I had already ask a local Helix screw pile contractor and I thought it was a keen price but could not get his mini digger around it think it was someting like £800 per pile to a certian depth then so much a mtr so I dug a hole under footing and found some concrete blocks cut them in half and put on a 16 ton jack and jacked them into the ground and keep putting a new half block untill it would not go down any more then i went all around the garage,rear I went down about 1.7mtrs front over 2 mtrs.Then put a few jacks under totaling 72 tons and jacked up the back 6" .I had a few trench acrows cut them down and put them under the footings and concreted them in,then dug under footings between piles and concreted under then drilled through floor and washed sand under floor
 

Attachments

  • IMG_20200526_092945.jpg
    IMG_20200526_092945.jpg
    256.5 KB · Views: 278
  • IMG_20200602_140012.jpg
    IMG_20200602_140012.jpg
    376.8 KB · Views: 288
  • IMG_20200608_090548.jpg
    IMG_20200608_090548.jpg
    215.1 KB · Views: 249
  • IMG_20200602_140032.jpg
    IMG_20200602_140032.jpg
    295.1 KB · Views: 261
Last edited:
V8Druid

V8Druid

do it as well as you can,but learn to do it better
last year during first lockdown I got a bit bored and decided to lift my garage up about 6" at the back I had already ask a local Helix screw pile contractor and I thought it was a keen price but could not get his mini digger around it think it was someting like £800 per pile to a certian depth then so much a mtr so I dug a hole under footing and found some concrete blocks cut them in half and put on a 16 ton jack and jacked them into the ground and keep putting a new half block untill it would not go down any more then i went all around the garage,rear I went down about 1.7mtrs front over 2 mtrs.Then put a few jacks under totaling 72 tons and jacked up the back 6" .I had a few trench acrows cut them down and put them under the footings and concreted them in,then dug under footings between piles and concreted under then drilled through floor and washed sand under floor
why?? .. had it dropped?
 
Bob

Bob

Well-known member
why?? .. had it dropped?
when I built my home 30 odd years ago I had may gurney pile the bungalow when I went to build the garage I had a problem with a nieghbour about piling my garage so the building inspector agreed I could raft it and it was worked out it would sink about 4" trouble was it sank more at the back than the front
 
V8Druid

V8Druid

do it as well as you can,but learn to do it better
when I built my home 30 odd years ago I had may gurney pile the bungalow when I went to build the garage I had a problem with a nieghbour about piling my garage so the building inspector agreed I could raft it and it was worked out it would sink about 4" trouble was it sank more at the back than the front
that was annoying :rolleyes::(:(
 
6

6feetdown

Well-known member
how did this go did you have to tighten up the gap after you concreted it and stitch brickwork or was it concrete it and leave
We've concreted, reinstated patio but hope to go back later this week to tie it back.
Said to the client it may be worth taking down that section next year as it moved a little more when carrying out the work even when propped.
I dont think it helped he'd had a 2 foot hole open for 6 months
 
D

DaveDCB

Well-known member
Luckily so far anything I’ve come across which needs under pinning is single story, works out a lot less hassle to knock it down and rebuild of decent footings. Plus no issues when you come to sell ref warranty
 
6

6feetdown

Well-known member
Luckily so far anything I’ve come across which needs under pinning is single story, works out a lot less hassle to knock it down and rebuild of decent footings. Plus no issues when you come to sell ref warranty
This 1 was too. The problem was it was a big extension with limited access thats why they decided on the underpinning route
 