So clients didnt like the rock idea so we're doing 3 walls out of slate slabs - sleepers - slate posts as per photos below.
View attachment 59179View attachment 59180View attachment 59181
First 2 lifts will have a set of steps in and the rest will be made of mix of uprights slate and sleepers, ground is slate/stone that will be hard going, the height will be about 1.2m high and we are planning to order 2m lengths of everything and get as much as poss concreted in as poss, ripper should come in to pull trench, then back them with product below
View attachment 59183before drain in bottom and clean stone backfill.
Question is ...any tips for the job, setting out etc they are fair lumps so we will need a pretty efficient way of going about it, dont wont a lot of double handling and messing...as per useful any usual advice very welcome