Hi folks I'm just double checking that what I'm charging is a correct hourly rate for an operator and hire for a 2.5ton digger.......£28 + diesel?
I'm based in Scotland about 10miles south of Glasgow I'm doing work on new house projects,caravan parks,driveways and some landscaping
 
Furniss

Furniss

Well-known member
Why wouldn’t it be??
I’ve always done it, never had any issues in doing so. I did end up with a spreadsheet with all my customers and different prices for everyone on, easier jobs/customers got charged less, hardwork was more 😉
Yes it makes sense ...comes down to character - some of us are better business people than others in that regard.
 
F

fred

Well-known member
350+vat a day, even then you be working for minimum wage after deducting all your overheads.
 
Simon edwards

Simon edwards

Well-known member
I have a couple of regular customers that give us a lot of work and their rates are a little lower than a one off customer, it’s the extras that make the difference really, machine and operator plus a dumper, wacker plate, breaker etc. plus a ground worker stacks up well. Operated machine alone even on reasonable rates only just works financially,in my experience the smaller machines do give a far better margin due to lower cost of ownership,it’s a pretty tough game these days really.
 
Nick...

Nick...

Well-known member
You want £50 an hour.sit down and work out your costs.I did mine during covid.I was charging £33 hour at time and I was massivly under charging.to hire a 2.5/3 ton machine here is £100 day.just took this from a local hire company price list.another £150 day for operator which ain't enough self employed taking into account non working wet days,looking at jobs,site meetings and paperwork,all unpaid.30 litres of diesel a day at around £50.insurance and maintenance on top of that and 20/25% for profit and you can do the maths.plus transport on top.I've charged £25 each way for 10/15 miles but people complain at times.not cheap running a newish hilux and ifor.after 40 years I've really had enough and I do the odd job with my machine but do operate a couple of takeuchi diggers for a builder customer who is my best mate and if he was not my mate I would not do it.I've got 40 years of experience too which I advise people with having done most things in this time.plenty of people hire diggers because they think it's easy and then make major f**k ups.I've done loads over the years clearing up and sorting out problems after people hire machines and make a complete cock up of things.
nick...
 
heritage machining

heritage machining

Well-known member
250 a day basic then at least 100 machine hire plus attachments plus diesel plus transport if a short job gotta allow at least a hr for transport even if close by loading unloading ECT. welding and body work on cars which I also do is 60 an hr plus gas wire consumables all plus vat
 
V8Druid

V8Druid

do it as well as you can,but learn to do it better
250 a day basic then at least 100 machine hire plus attachments plus diesel plus transport if a short job gotta allow at least a hr for transport even if close by loading unloading ECT. welding and body work on cars which I also do is 60 an hr plus gas wire consumables all plus vat
I know which I'd rather NOT be doing .. hateful, thankless task :(
 